Piccadilly Gate
This project involved the full refurbishment and fit-out of a 10 storey building to a high standard and excellence with regards to sustainability and the environment.
Work completed now provides office accommodation space for a number of government agencies.
Specific work included:
- The complete strip-out of the existing building
- Refurbishment of all floors, including an entirely new mechanical & electrical solution
- Construction of new curtain walling and cladding system to provide a new envelope to the entire building
- Construction of new external fire escapes
Ocon completed the refurbishment of Piccadilly Gate which included fully air conditioned spaces throughout to create a series of spacious and contemporary working environments.
The performance standards have achieved the BREEAM ‘excellent’ environmental sustainability rating and incorporate cutting edge design and technological features to satisfy the demand of the modern occupier.
Project Team
Client: BRB (Residuary) Ltd
Architect: Archial
M&E: SES
Project Manager: Turner & Townsend
Form of Contract: JCT Design & Build 2005
Start on Site: September 2008
Completion: April 2010
Contract Period: 76 weeks
Value: £25m